Group meeting on Thursday 10/21. Meeting duration: 1 hour. All members in attendance.
Topics discussed:
- Began brainstorming for report and presentation.
- Drafted email to professor with questions about the course requirements.
- Pending response from professor and NEFAR representative, parts will be ordered no later than 10/27.
- Compiled a partial list of misc. construction supplies that will be sourced locally (primer, paint, clear coat, epoxies, etc.).
To Do:
- Email professor.
- Email NEFAR representative
- Continue building outline for report and presentation.
- Assess buying/making an altimeter for the rocket.
Group meeting on Thursday 10/7. Meeting duration: 45 minutes. All members in attendance.
Topics Discussed:
Finalized list of what has to be purchased and what can be made in house.
Make:
- Bulkheads
- Fins
- Centering Rings
- Ejection System
- Parachute + free bag
- Window (for camera)
Purchase:
- Body tube
- Nosecone
- Motor
- Motor Mount
- Camera
To do for next meeting:
- Finalize parts list to order
- Continue designing in the NASA software, and possibly make some test builds in RockSim.